1526	[super] Update and test existing DGU package form	icmurray	icmurray	"Re-create behaviour of old form without using form-alchemy.  And unit test.

 * [X] write high-level functional tests for the form.  Creation / edition / validation.
       Original estimate: 6 days (3 days x 2)
              Time spent: 3 days
          Time remaining: 0 days

 * [X] write the html
       Original estimate: 2 days (1 day x 2)
              Time spent: 1.3 days
          Time remaining: 0 days

 * [X] modify the existing validation schema
       Original estimate: 2 days (1 day x 2)
              Time spent: 1.3 days
          Time remaining: 1 days

 * [X] split resources into types: individual, time-series, and additional.
       Original estimate: 2 days
              Time spent: 2.5 days
          Time remaining: 0 days

 * [X] contact information is derived from Publisher, but can be altered for each dataset. [#1617]
       Original estimate: 4 days
              Time spent: 0 days
          Time remaining: 4 days
       (Waiting on publisher integration)

 * [X] foi contact information is derived from user, but can be altered for each dataset. [#1617]
       Original estimate: 1 days
              Time spent: 0 days
          Time remaining: 1 days
       (Waiting on publisher integration)

 * [X] provide stubs for the theme and sub-themes [#1618]
       Original estimate: 1 days
              Time spent: 0 days
          Time remaining: 0 days

 * [X] provide stubs for the publisher hierarchy [#1619]
       Original estimate: 2 days
              Time spent: 0.5 days
          Time remaining: 1.5 days
     Note - the groups refactor is essentially ready to be used. And this would be a good test case for it.

 * [X] don't allow package-type selection when editing a package
     Can't change a dataset from containing time-series resources to one containing individual resources or visa-versa. (#1620)
       Original estimate: 0.5 days
              Time spent: 0 days
          Time remaining: 0 days
"	enhancement	closed	major	ckan-sprint-2012-03-05	dgu	fixed	dgu form refactor	dread kindly shevski	ckanext-dgu	none